Quality Roofing recently completed the roof replacement at Shawano Community Middle School, following earlier work on the district’s high school.

Roofing System Details

  • The existing modified roof was fully removed down to the wood deck.
  • A 2.5-inch base insulation layer was installed, followed by an 8th-inch per-slope tapered insulation system to ensure proper drainage.
  • Another 2.5-inch insulation layer was fastened over top for added performance.
  • A ½-inch high-density cover board was installed before adhering the new 60 mil black EPDM membrane.

Project Notes

This project was a full tear-off and rebuild, providing the school with a durable and efficient new roof system. During the work, the crew even encountered a bat that had found its way into the building. It was safely released back into the wild—a small reminder of the unexpected moments that can happen on the job.